Questions to Ask a Builder Before Signing a Contract

Good builders welcome thorough questions before a contract is signed. Use these ten practical questions to check inclusions, allowances, supervision and variation rules.

By Builders of Oz Editorial TeamPublished: 2026-09-24Last reviewed: 2026-10-28
Building contract specifications, architectural plans and hard hat on a timber table

Quick Answer

Before signing any building contract, verify five core areas in writing: (1) current builder registration/licensing and mandatory insurances for your state and project type, (2) a line-by-line inclusions and exclusions schedule, (3) realistic Prime Cost (PC) and Provisional Sum (PS) figures, (4) who will supervise your site day-to-day and how often you will receive updates, and (5) the exact written process for approving variations and timeline extensions.

1. Licensing, Registration and Insurance Verification

Every Australian state and territory maintains a public register for licensed builders and trade contractors, along with statutory rules for contract forms, deposit caps and domestic building / home warranty insurance.

  • Ask: "Which legal entity is entering into the contract, and can we confirm the matching builder licence/registration details and insurances?"
  • Check that the company name on the quote matches the licensed entity on the contract and insurance certificates.

2. Scope Clarity: Inclusions, Exclusions and Allowances

Never assume an item shown on an architectural 3D render is automatically included in the contract sum unless it appears in the written specification.

  • Ask: "Can you walk me through everything explicitly excluded from this quote—such as driveways, fencing, landscaping, window blinds, demolition or authority fees?"
  • Ask: "How were each of the Prime Cost (PC) and Provisional Sum (PS) allowances calculated, and can I supply or select actual models now to lock in fixed pricing?"

Practical example: Checking tile allowances

If a bathroom quote lists a PC supply allowance of $30/m² for tiles, yet the porcelain tiles you like retail at $85/m²—and require mitred edges rather than aluminium trim—clarifying both supply rate and laying complexity before signing prevents a surprise four-figure adjustment.

3. Site Supervision and Workload

The person you meet during quoting is not always the person running your site each week. Understanding site leadership matters.

  • Ask: "Who will be my day-to-day site supervisor, how many active sites do they oversee at once, and how will we communicate each week?"
  • Ask: "Which quality hold-point walkthroughs will we attend together on site?"

4. Programme Realism and Lead Times

A realistic start date and completion window beats an overly optimistic promise made just to win a signature.

  • Ask: "Once permits and pre-start selections are complete, when can site work genuinely start—and which long-lead materials could affect the critical path?"
  • Ask: "What selection deadlines do you need from me so I never hold up trades?"

5. Variations and Dispute Resolution

Standard-form industry or state fair-trading building contracts exist to protect both client and builder with clear rules.

  • Ask: "Which standard building contract form do you use, and how are client-requested or latent-condition variations priced and signed off before work proceeds?"
  • Tip: Always read the full contract—and seek independent legal or specialist review if anything is unfamiliar—before signing.

Key Takeaways

  • Verify that entity names, licences and insurances match across quotes and contracts.
  • Scrutinise low Prime Cost or Provisional Sum allowances—realistic upfront figures protect your budget.
  • Confirm explicit exclusions in writing so nothing falls between builder and owner.
  • Insist on written variation sign-off and regular scheduled progress updates.